Hi ,
I have to create an analysis for a large assembly where:
1 in the first step I have to pretension some screws
2 then I have to apply a press fit
3 then have to pretension some other screws
4 apply some loads
My question would be, if I create a PCONT with CLEARENCE option for the press fit, how can I be sure that this will make his effect just in the second step by me and only there and not on every other steps too, since for this option there is no need for an explicit loadstep.
Thanks and regards,