cntnlsub control card question
hi cae eigineerings,
i have question for control card question "cntnlsub"
my analysis is implicit problem and i know time in this implicit is no meaning.(sorry my english is poor )
if i use this card, i have two step,the second step continue first.
so when i using hyperview plot ,my x axis will show time 1 and time 2 ?
Best Answer
-
Hi Tonychen,
Yes, time will not be a physical time, increment of the load.
In the HyperView session you will see from 0 to 1 for the subcase 1, and from 1 to 2 for the subcase 2. You can use Derived Load Steps for plotting from 0 to 2 directly.
Don't forget to use NLOUT for requesting intermediate results.
Thank you very much,
2
Answers
-
Hi Tonychen,
Yes, time will not be a physical time, increment of the load.
In the HyperView session you will see from 0 to 1 for the subcase 1, and from 1 to 2 for the subcase 2. You can use Derived Load Steps for plotting from 0 to 2 directly.
Don't forget to use NLOUT for requesting intermediate results.
Thank you very much,
2 -
Robinson Ferrari_20451 said:
Hi Tonychen,
Yes, time will not be a physical time, increment of the load.
In the HyperView session you will see from 0 to 1 for the subcase 1, and from 1 to 2 for the subcase 2. You can use Derived Load Steps for plotting from 0 to 2 directly.
Don't forget to use NLOUT for requesting intermediate results.
Thank you very much,
thanks a lot.
0